Rivals Say Halliburton Dominates Iraq Oil Work
By NEELA BANERJEE, NY Times
August 8, 2003

The Bechtel Group, one of the world's biggest engineering and construction
companies, has dropped out of the running for a contract to rebuild the
Iraqi oil industry, as other competitors have begun to conclude that the
bidding process favors the one company already working in Iraq, Halliburton.

After the United States Army Corps of Engineers quietly selected Halliburton
in the spring to perform early repairs of the Iraqi oil business in the
aftermath of the war, other companies and members of Congress protested that
the work should have been awarded through competitive bidding.

Halliburton's role in the rebuilding has been under political scrutiny
because the company was formerly headed by Vice President Dick Cheney. But
the Bush administration and the Corps of Engineers, which is overseeing the
Iraqi oil reconstruction effort, have repeatedly said that Halliburton has
no inside track.

Preliminary plans for a new contract, which industry executives had thought
might total $1 billion, were announced late in June by the Corps of
Engineers. The bidding was meant, in part, to introduce competition and a
sense of fairness into the lucrative Iraqi reconstruction market, an
executive with a major engineering concern said. Like many industry
executives, he would speak only on condition of anonymity because his
company does not want to jeopardize its chances for future government
contracts.

But in the last month, the corps, which is overseeing the reconstruction
efforts, has specified a timetable for the work that effectively means that
the value of any contract companies other than Halliburton could win would
be worth only about $176 million, according to Corps of Engineers documents
and executives in the engineering and construction business.

Earlier this week, Bechtel cited the timetable as its reason for dropping
out of the bidding. The company now plans to deal directly with the Iraqi
oil ministry for future reconstruction work, a spokesman, Howard N. Menaker,
said.

Although the oil ministry and the Army Corps of Engineers nominally
cooperate, industry analysts say the Americans have the upper hand.

Officials of the Corps of Engineers did not return numerous phone calls
yesterday seeking comment on the contract. But last month, in response to
questions from other companies about Halliburton's role, the corps said on
its Web site that all potential bidders had received the same information to
"eliminate any competitive advantage" Halliburton might have from its
involvement in the Iraqi reconstruction work so far.

A spokeswoman for Halliburton, Wendy Hall, would not discuss whether its
engineering unit, Kellogg Brown & Root, would bid, saying only that "we will
evaluate the opportunity."

After indicating in June that it planned to solicit bids, the Corps of
Engineers held a conference of prospective bidders in Dallas on July 14.
Records of the meeting show that it was attended by some of the most
experienced engineering and construction companies in the world ? including,
besides Halliburton and Bechtel, Fluor, the Parsons Group, Schlumberger and
Foster Wheeler.

Among those companies, only Fluor and Parsons have indicated so far that
they plan to make bids by the Aug. 14 deadline. A winner will be announced
by Oct. 15, according to the Corps of Engineers.

At the meeting and in the initial request for proposals, the Corps of
Engineers put forth what the industry calls "an indefinite quantity,
indefinite delivery" contract. Industry executives said they were told there
could in fact be two principal contracts, one for the oil industry in
northern Iraq and the other for the south. The value of each contract could
range from $500,000 to $500 million over several years, according to the
Corps of Engineers, which cited the continued instability in Iraq as a
reason for keeping the terms so vague.

A transcript of the July meeting shows that bidders were concerned even then
that Halliburton would have a competitive advantage over other companies
because it was already working with the Corps of Engineers in Iraq and
helping to assess the repairs needed at oil production sites and pipelines
after the war and years of an economic embargo.

The corps denied that such a conflict of interest existed, according to the
transcript.

Over the last three weeks, however, the Corps of Engineers has provided
additional information to bidders indicating that by the July meeting, it
and Halliburton already had a fairly clear understanding of the scope and
financial value of the work to be done and the timetable for completing it.

The newly released information indicates that a week before the Dallas
meeting, the Corps of Engineers and Halliburton participated in a large
workshop in Baghdad that also included representatives of the Iraqi oil
ministry and the ruling Coalition Provisional Authority to draw up a
detailed plan for rebuilding much of the Iraqi oil industry by the end of
March 2004.

A week ago, the Corps of Engineers Web site carried an amendment to the
contract proposal, saying that 220 projects, mostly at installations above
the ground, must be completed for Iraq's oil production to reach prewar
levels. The projects are divided into three phases, with a total estimated
cost of $1.14 billion.

But the corps notes in the plan that the first two phases, which together
would require about $967 million in investments, would have to be completed
by Dec. 31.

Halliburton's competitors worry that if the winner of the new contracts is
not announced until Oct. 15, that company could not even begin the work
before year's end. The only company that could do the work based on that
timetable is Halliburton, its competitors say.

Only the third and final phase, worth about $176 million and requiring the
work to be completed by March 31, could realistically be performed by a
Halliburton competitor, its rivals say.

"The feeling at our company was `Yes, Halliburton is the incumbent, but we
had an opportunity there,' " a representative of another engineering concern
said. "But if we had believed that from the beginning we had no chance of
winning this, we wouldn't have bid."

Responding to pointed questions about the timetable by potential bidders,
the Corps of Engineers' Web site said the proposed schedule was "not
intended to change anything" about the bidding process.

For its part, the Kellogg Brown & Root unit of Halliburton will do whatever
work the corps gives it, Ms. Hall, the spokeswoman, said.

"It is not known at this time how or if the future award of another Corps of
Engineers contract will affect current K.B.R. operations or the terms and
conditions of its contract," she said.

The first wave of Halliburton employees arrived in Iraq in March, to oversee
the extinguishing of several oil well fires near Basra. Since then, its
responsibilities, under the direction of the Corps of Engineers, have
expanded from its initial job of making emergency repairs.

Working in Iraq has helped turn around Halliburton's financial performance,
its second-quarter results showed. The company made a profit of $26 million,
in contrast to a loss of $498 million in the period a year earlier. The
company stated that 9 percent, or $324 million, of its second-quarter
revenue of $3.6 billion came from its work in Iraq.

-----------------------------------------------------------

 次へ  前へ

戦争38掲示板へ



フォローアップ:


 

 

 

 

  拍手はせず、拍手一覧を見る


★登録無しでコメント可能。今すぐ反映 通常 |動画・ツイッター等 |htmltag可(熟練者向)
タグCheck |タグに'だけを使っている場合のcheck |checkしない)(各説明

←ペンネーム新規登録ならチェック)
↓ペンネーム(2023/11/26から必須)

↓パスワード(ペンネームに必須)

(ペンネームとパスワードは初回使用で記録、次回以降にチェック。パスワードはメモすべし。)
↓画像認証
( 上画像文字を入力)
ルール確認&失敗対策
画像の URL (任意):
投稿コメント全ログ  コメント即時配信  スレ建て依頼  削除コメント確認方法
★阿修羅♪ http://www.asyura2.com/  since 1995
 題名には必ず「阿修羅さんへ」と記述してください。
掲示板,MLを含むこのサイトすべての
一切の引用、転載、リンクを許可いたします。確認メールは不要です。
引用元リンクを表示してください。